GDh. Maavarulu Airport Building (Phase 2)

Status

completed

About This Project

GDh. Maavarulu Airport Building Phase 2 project was handed over to MTCC by Ministry of Transport and Civil Aviation on 25th July 2019. 

Work being conducted under the project includes

  • Development of Passenger Terminal Building
  • Development of fire Building, staff quarter
  • Development of powerhouse, guard post, restaurant and a fire pond 

 

The MVR 12.1M project is estimated to be completed within 150 days.  

The  project was completed on 30th June 2020.

 

Project Tpe
Airport Construction
Location
G.Dh. Maavarulu
Client
Ministry of Transport and Civil Aviation
Contract Sign Date
25th July 2019
Completion Date
30th June 2020