Awarded in 2015, Phase two of G.Dh. Gahdhoo Harbour project was signed between MTCC and the Ministry of Housing and Infrastructure. The project was completed in 2018.
This project included:
Dredging: Maint. dredging of new harbour basin – 17,236.0 Cbm, Maint. dredging of existing channel -100.0 Cbm, Maint. dredging of existing basin- 1000.0 Cbm
Breakwater & revetment: Breakwater construction (B-B) -221.0 m, revetment- 25.0m
Quaywall: QW block installation – 267m
Sundries: Harbour pavement – Installation of blocks – 3055.0 Sqm, harbour lights – installation of lights – 13.0nos, beacon installation – 2nos