Dh. Bandidhoo Harbour Project

Status

completed

About This Project

Dh. Bandidhoo Harbour Project was awarded to MTCC on 9th February back in 2014. The work for this project, awarded by the Ministry of Housing and Infrastructure, was completed on 14th August 2017.

 

The scope of this project included:

Dredging/excavation of new harbour basin, maximum specified depth of -3m MSL; Total dredge volume is 30,451.30 CBM

Dredging/excavation of new entrance channel, maximum specified depth of -3m MSL; Total dredge volume is 502.70 CBM

Construction of rock boulder breakwater of total length 413.31m

Construction of rock boulder revetment of total length 91.61m

Supply and installation of 2 Nos of navigational lights

Extension of quwaywall by 198.12m

Construction of interlocking pavement to the length of the harbour with a width of 5m; total 1,535 SQM

Project Tpe
Harbour Construction
Location
Dh. Bandidhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
9th February 2014
Project Start Date
10th March 2014
Completion Date
14th August 2017