Design & Build of Gn.Fuvahmulah City Internal Road

Status

on-going

About This Project

The project to develop the internal road of Fuvahmulah was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure on 4th July 2019.

Work commenced following transfer of required excavators and cable junctions to the project site. The project will see the development of 31 roads with an overall length of 15,932m.

This project includes

  • Development of sub-base preparation-excavation & compaction of sqm 122,659.00
  • Base preparation & Asphalt Wearing Course
  • Road Markings
  • Developing footpath preparation & road crossing
  • Setting up road signage & street lights
  • Establishing storm water drainage works 

The MVR 279.4 million project is to be completed early next year.

Project Tpe
Road Construction
Location
Gn. Fuvahmulah
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
4th July 2019
Project Start Date
23rd July 2019