Design and Build of Sh. Lhaimagu Harbour

Status

on-going

About This Project

We have mobilized Sh. Lhaimagu Harbour project site on 07th December 2020.

Work on Design and Build of Sh. Lhaimagu Harbour is well underway. New harbor basin dredging works for the project is currently ongoing, with 50% completion.

Scope of the project includes
  • Dredging and excavation operations of 31,000cbm
  • Construction of a 350m breakwater
  • Construction a 500m revetment
  • Construction a 276m quay wall
  • Installation of 1,380sqm paved area
  • Installation of streetlights
The value of the project is MVR 56.3 million.
Project Tpe
Harbour Construction
Location
Sh. Lhaimagu
Client
Ministry of National Planning, Housing and Infrastructure
Project Start Date
7th December 2020