Design and Build of Sh.Komandoo Harbor Upgrade

Status

completed

About This Project

Design and Build of Sh.Komandoo Harbor Upgrade was awarded to MTCC by Ministry of National Planning, Housing and Infrastructure on 4th August 2019

Scope of the project includes

  • Channel Dredging 14,731cbm
  • Maintenance & New harbor basin 
  • Dredging35,348cbm 
  • Developing 12m Breakwater
  • Developing 20m Revetment 20m
  • Developing 190m Quay wall
  • Developing 1,991sqm Pavement
  • Installation of 2 navigation lights
  • Installation of two arm streetlights, Mooring buoys and 190m rock apron 

The MVR 29.41M project is to be completed within 365 days.

Project Tpe
Harbour Construction
Harbour Redevelopment
Location
Sh. Komandoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
29th December 2019
Completion Date
27th December 2020