Design and build of harbor upgrade in F.Dharanboodhoo

Status

on-going

About This Project

The project to re-develop the harbor of F.Dharanboodhoo was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure on 10th December 2019. 

Work conducted under the project includes

  • Dredging and Excavation 46,600Cbm
  • Construction of 410m breakwater
  • Construction of 64m revetment
  • Construction of 196m quay wall
  • Construction of Ramp
  • Installation of Harbor lights
  • Installation of Mooring blocks and 2,500sqm of Paved area

The MVR 38.2M project is estimated to be completed within 397 days. 

Project Tpe
Harbour Redevelopment
Location
F. Dharanboodhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
10th December 2019