Design and Build of Harbor Upgrade in Dh. Hulhudheli

Status

on-going

About This Project

The project to re-develop the harbor of Dh. Hulhudheli was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure on 10-12-2019.

Work conducted under the project includes

  • Dredging & Excavation 45,585cbm
  • Construction of 60m Groynes 
  • Construction of 432m quay wall  
  • Development of 227m breakwater
  • Development of 60m revetment
  • Construction of Ramp
  • Installation of streetlights 
  • Installation of Mooring blocks and 2,160sqm of paved area 

The MVR 39.8M project is estimated to be completed within 362 days.

Project Tpe
Harbour Redevelopment
Location
Dh. Hulhudheli
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
10th December 2019