Design and Build of H.Dh. Hanimaadhoo Harbour Upgrade

Status

on-going

About This Project

MTCC was awarded the design and build of H.Dh. Hanimaadhoo harbour upgrade on 24th September 2019. The work for this project, contracted by the the Ministry of National Planning and Infrastructure, has not yet started.

Work on Hdh. Hanimaadhoo Harbour is well underway, with overall 26% project progress. The cutter dredger with equipment have been delivered to the project site on 12th December 2020.

The scope for this project includes:

  • Dredging of 53,522.50cbm for New harbor basin
  • Dredging 31,575.50cbm for entrance channel
  • Construction of a 355m breakwater
  • Construction of a 50m revetment
  • Construction of 270m quay wall
  • Installation of 2,583sqm of paved area

The project is to be completed shortly.

Project Tpe
Harbour Construction
Location
H.Dh. Hanimaadhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
24th September 2019