About This Project

Design and build shore protection structure at R. Fainu was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure.
The agreement relating to the project was signed by CEO Adam Azim signed on behalf of MTCC and Permanent Secretary Zeeniya Ahmed Hameed signed on behalf of the MNPHI.
Scope of the project includes
  • Construction of a 8100cbm of backfilling and bed preparation works
  • Construction of 250m geo bag revetment
The value of the project is MVR 8.96 million and the project is to be completed within 180 days.
Project Tpe
Shore Protection
Location
R. Fainu
Client
Ministry of National Planning Housing and Infrastructure
Contract Sign Date
29th March 2021