Design and build of M.Veyvah harbour upgrading project

Status

on-going

About This Project

The construction of M. Veyvah harbour upgrade was awarded to MTCC on 27th August 2019 by  the Ministry of National Planning and Infrastructure.

This project includes:

  • Dredging, Excavation of 56,925 cbm new basin 
  • Dredging, Excavation of 3,914cbm new channel
  • Precast blocks delivery, block installation, cast in-situ wall casting 
  • Placing of interlock paving
  • Installation of Street Lights 
  • Breakwater construction 
  • Revetment construction
  •  Navigation Light installation 

The value of the project is MVR 48.8 million.

Project Tpe
Harbour Construction
Location
M. Veyvah
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
27th August 2019
Project Start Date
10th September 2019