B. Thulhaadhoo Harbour Project

Status

completed

About This Project

B. Thulhaadhoo Harbour Project was awarded to MTCC on 9th February back in 2014. The work for this project, awarded by the Ministry of Housing and Infrastructure, was completed on 25th December 2017.

 

The scope of this project included:

Construction of rock boulder breakwater of total length 537.68m

Construction of rock boulder revetment of total length 197.50m

Supply and installation of 2 nos of navigational lights

Quwaywall installation of total length 184.86m

Construction of interlocking pavement to the length of the harbour with a width of 5m; total 1,855 SQM

Project Tpe
Harbour Construction
Location
B. Thulhaadhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
9th February 2014
Project Start Date
17th November 2014
Completion Date
25th December 2017