B. Thulhaadhoo Harbour Project was awarded to MTCC on 9th February back in 2014. The work for this project, awarded by the Ministry of Housing and Infrastructure, was completed on 25th December 2017.
The scope of this project included:
Construction of rock boulder breakwater of total length 537.68m
Construction of rock boulder revetment of total length 197.50m
Supply and installation of 2 nos of navigational lights
Quwaywall installation of total length 184.86m
Construction of interlocking pavement to the length of the harbour with a width of 5m; total 1,855 SQM