Harbour Construction of A.A. Himendhoo

Status

completed

About This Project

The project to construct A.A. Himendhoo’s harbor was completed on 20th April 2020.

Work done under the project includes:

Dredging of harbor basin 20,330.00 cbm

Entrance channel dredging 15,187.50 cbm

Rock armor breakwater 140.50 m

Rock armor revetment 70 m

Construction of Quay wall 170 m

Beacon Installation 4 nos

Harbor paving works 540 Sqm

Supply and installation of street lights 8 nos

The project was signed between MTCC and Ministry of Housing and Infrastructure on May 15th, 2018. Permanent Secretary at the Ministry of Planning and Infrastructure, Zeeniya Ahmed Hameed signed on behalf of the government and the COO of MTCC Shahid Hussain Moosa, signed on behalf of the company.

Category
Dredging and Reclamation
Project Tpe
Harbour Construction
Location
A.A. Himendhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
15th May 2018
Project Start Date
27th August 2018
Completion Date
20th April 2020