Harbour Construction

A.Dh. Dhangethi Harbour Project

A.Dh. Dhangethi Harbour Project was awarded to MTCC on 9th February back in 2014. The work for this project, awarded by the Ministry of Housing and Infrastructure, was completed on 121st August 2018.

 

The scope of this project included:

Basin dredging – 33,553cbm,

Channel dredging -24,013cbm,

Harbour pavement 1070sqm

Breakwater construction 317m

Revetment -41m

Status
completed
Project Type
Harbour Construction
Location
A.Dh. Dhangethi
Client
Ministry of Housing and Infrastructure
Contract Sign Date
9th February 2014
Project Start Date
14th March 2014
Completion Date
21st August 2018