Project works on design and build of coastal protection structures at N. Fohdhoo is well underway

Project works on design and build of coastal protection structures at N. Fohdhoo is well underway, with project completion targeted by end July, 2020. We are currently working on geobag laying needed for revetment construction.
The project, which is aimed to solve increasing erosion issues faced by the island, involves sand filtering works of 1,400cbm; sand filling for geo bags; and sand backfilling works of 5,000cbm. It also involves laying of geo bags along a 180m area.

The estimated value of the project is MVR 7.6 million. The project was awarded on 25th February 2020 and received EIA Approval on 18th March 2020.

No Comments

Sorry, the comment form is closed at this time.