MTCC has signed an agreement with Ministry of Construction and Infrastructure towards the implementation of Land Reclamation & Shore Protection of the land to be used for t
B. Eydhafushi Harbor Development Project is well underway. Channel dredging and existing harbor dredging operations are ongoing, with 97% and 87% completion respectively. I
Ha. Dhihdhoo Harbor Extension and Jetty Construction Project is well underway, with overall 87% project progress. Breakwater profiling and revetment profiling works are cur
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is well underway, with overall 93% project progress. Construction of a jetty at south side of the ha
Th. Kinbidhoo Land Reclamation Project is well underway. Reclamation operations are ongoing, with 30% completion.
Ga. Villingili Harbor Development Project (Phase 3) is well underway, with overall 52% project progress. Installation of anchor blocks for quay wall construction and harbor
Work on F. Magoodhoo Land Reclamation and Shore Protection Project is well underway, with overall 53% project progress. Rock boulder shipments have been delivered to the si
R. Kinolhas Shore Protection Project is well underway, with overall 76% project progress. Reclamation and compaction operations are currently ongoing, with 75% completion.
N. Velidhoo Junior College Project is well underway. We have completed external walls masonry works. Internal masonry works are ongoing. Scope of works include, constructio
The AA. Feridhoo Harbor Development Project is currently ongoing. Quay wall block installation work has been completed, and new harbor basin dredging work has reached 91% c
Ha. Muraidhoo Harbor Development Project is well underway, with overall 90% project progress. We have completed breakwater profiling works. Scope of works include, 28,175cb
Gdh. Rathafandhoo Shore Protection Project is well underway, with overall 60% project progress. We have completed construction of breakwater. Scope of works include, constr
Sh. Maaungoodhoo Harbor Development Project is currently underway with 70% project completion. The second shipment of rock boulders has been delivered to the project site,
The first shipment of quay wall blocks required for the Hdh. Kurinbi Harbor Development Project have been delivered to the project site. Quay wall block installation work i
The first shipment of quay wall blocks required for the Hdh. Neykurendhoo Harbor Development Project has been delivered to the project site, and quay wall block installatio
B. Maalhos Harbor Repair and Shore Protection Project is well underway. New harbor basin dredging operations are ongoing, with 54% completion. Installation of concrete bloc
B. Kamadhoo Harbor Development Project is well underway, with overall 93% project progress. Revetment profiling work and entrance channel dredging operation is ongoing, wit
Sh. Milandhoo Harbor Development Project is well underway. New harbor basin dredging operations are ongoing, with 31% completion. Harbour paving work is ongoing with 22% co
We have mobilized Hdh. Finey Harbor Development Project site on 3rd July 2024. Scope of works include, 5,848.05cbm maintenance dredging operations, 35,484.26cbm new harbor
Sh. Bilehfahi Harbor Development Project is well underway, with overall 86% project progress. Fourth shipment of rock boulders required for the project have been transferre
N. Lhohi Harbor Development Project is well underway. Quay wall concrete works are ongoing, with 44% completion. Scope of works include, 66,701cbm maintenance dredging oper
Sh. Noomaraa Harbor Development Project is well underway. New harbor basin dredging operations are ongoing with 51% completion. First shipment of concrete blocks required f
The seventh shipment of rock boulders required for the Sh. Milandhoo Shore Protection project has been delivered to the site. Furthermore, the revetment profiling work and
We have commenced Geobag revetment works at R. Kinolhas Shore Protection Project site. Additionally, reclamation and compaction work is ongoing at the site with overall pro
The third shipment of rock boulders required for the Ha. Dhidhoo Harbor Extension & Jetty project has been delivered to the site. Furthermore, the variation works of quay w
N. Kendhikulhudhoo Harbor Upgrade and Boat Beaching Area Project is well underway. New harbor basin dredging operations are currently ongoing, with 67% completion. Scope of
We have mobilized Aa. Himendhoo Shore Protection Project site on 30th April 2024. Scope of works include, 43,200cbm beach nourishment operations, construction of 110m rockb
We have mobilized the project site for the ADh. Dhangethi Harbor Development Project on 18th April 2024. Scope of works for the project include, 35,500cbm land reclamation
We have mobilized V. Thinadhoo Harbor Development Project site on 16th April 2024. Scope of works include, 12,800cbm new harbor basin dredging operations, 860cbm channel dr
We have mobilized the L. Maavah Land Reclamation Project site on 16th April 2024. Scope of works include, land reclamation operations of 508,816cbm and search surveys. The
We have mobilized the GA. Kolamaafushi Land Reclamation Project on 3rd April 2024. Scope of works include, land reclamation operations of 284,145cbm, and installation of 82
F. Nilandhoo Harbor Development Project is well underway. First shipment of concrete blocks required for quay wall construction have been delivered to the site. Harbor basi
Ha. Baarah Channel and Maintenance Dredging Project is currently underway with 84% project completion. Full shipment of Geobags has been delivered to the project site, and
N. Lhohi Harbor Development Project is well underway. First shipment of concrete blocks required for quay wall construction have been delivered to the site. Scope of works
R. Ungoofaaru Land Reclamation and Shore Protection Project is well underway. Dredging and reclamation is ongoing, with 63% completion. Scope of works include, 10 hectares
B. Dharavandhoo Harbor Development Project is well underway. First shipment of concrete blocks required for quay wall construction, have been delivered to the project site.
Gdh. Rathafandhoo Shore Protection Project is well underway. Second shipment of rock boulders required for the project have been delivered to the project site. Construction
Work on F. Magoodhoo Land Reclamation and Shore Protection Project is well underway, with overall 50% project progress. We have completed island reclamation operations. Geo
We have commenced subbase preparation works for Sh. Funadhoo Football ground project on 12th February 2024. Scope of works include, excavation of 2,400cbm sand for subbase
Sh. Maaungoodhoo Harbor Development Project is well underway, with overall 55% project progress. We have commenced breakwater profiling works on 11 Feb 2024. Scope of works
N. Velidhoo Junior College Project is well underway. Column concrete works are ongoing. We have completed lean concrete and tie beam works. Scope of works include, construc
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway. Jetty column installation work has been completed, and barbending & concrete
Adh. Omadhoo Harbor Development Project is well underway. Third shipment of concrete blocks required for quay wall construction have been delivered to project site on 6th F
K. Maafushi Harbor Development Project is well underway. Second shipment of concrete blocks required for the quay wall construction, have been delivered to the project site
We have successfully completed Ha. Hoarafushi Juvenile Justice Unit (Halfway House) Project. Scope of works include, ground works, concrete works, masonry and plastering, r
We have successfully completed Adh. Kunburudhoo Shore Protection Project. Scope of works include, 24,000cbm dredging and reclamation operations, 430m rock boulder revetment
Aa. Rasdhoo Harbor Breakwater and Coastal Protection Project is well underway. The installation of concrete blocks required for quay wall construction is ongoing. Final shi
S. Hithadhoo Old Harbor Breakwater Construction Project (Phase 2) is well underway. Second shipment of concrete blocks required for quay wall construction have been deliver
Adh. Omadhoo Harbor Development Project is well underway. Second shipment of concrete blocks required for quay wall construction, have been delivered to the site. Quay wall
Second shipment of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project, have been delivered to the project site. Scope of works
S. Hithadhoo Old Harbor Breakwater Construction Project (Phase 2) is well underway. First shipment of concrete blocks required for quay wall construction have been delivere
K. Maafushi Harbor Development Project is well underway. Installation of concrete blocks for quay wall construction is ongoing, with 74% completion. Quay wall concrete work
We have mobilized the project site for the B. Maalhos Harbor Repair & Shore Protection Project 20th August 2023. Scope of works for the project include, maintenance dredgin
We have mobilized the project site for the N. Kudafari Shore Project 18th August 2023. Scope of works for the project include, construction of 220m groynes, 610m geobag rev
We have commenced installation of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project. Scope of works include, 17,900cbm mainte
Sh. Narudhoo Harbor Development Project is well underway. We have completed installation of blocks required for quay wall construction. Quay wall concrete works are ongoing
Hdh. Kumundhoo Harbor Channel Project is well underway, with overall 70% project progress. Fourth shipment of rock boulders required for the project work, have been deliver
We have mobilized Adh. Omadhoo Harbor Development Project site on 30th July 2023. Scope of works include, 49,765cbm dredging and excavation operations, 12,105cbm channel dr
Ha. Baarah Channel and Maintenance Dredging Project is well underway, with overall 70% project progress. We have completed channel dredging operations and harbor basin main
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is well underwayŘŚ with overall 55% project progress. We have completed channel breakwater operations
Second shipment of concrete blocks required for quay wall construction for Sh. Narudhoo Harbor Development Project have been delivered to the site on 17th July 2023. New ha
K. Maafushi Harbor Development Project is well underway. We have commenced installation of concrete blocks required for quay wall construction on 9th July 2023. Scope of wo
We have mobilized Aa. Bodufolhudhoo Land Reclamation and Shore Protection project site on 8th July 2023. Scope of works include, reclamation operations of 8 hectares, const
Meemu Airport Development Project is well underway, with overall 60% project progress. We have completed airport shore protection revetment works. In addition, subgrade wor
We have commenced physical works of Aa. Ukulhas Road Construction Project on 4th July 2023. Scope of works include, construction of 10 roads of 2678m. In addition, scope in
Second shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the site. Scope of works include, 24,000 cbm of dredging and
Quay wall block installation work for Sh. Maaungoodhoo Harbor Development Project has reached 98% progress. Quay wall concrete capping work is currently ongoing with 27% co
Work on Lh. Hinnavaru Harbor Development Project is currently underway with overall 90% project progress. Harbor excavation and sheet piling works have been completed, and
M. Muli Harbor Development Project is well underway. We have completed installation of concrete blocks required for quay wall construction. Construction of breakwater, pave
Sh. Narudhoo Harbor Development Project is well underway. First shipment of precast concrete blocks required for quay wall construction have been delivered to the site. Sco
We have mobilized Hdh. Kunribi Harbor Development Project site on 4th June 2023. Scope of works involve, new harbor basin dredging operations of 30,172 cbm, existing harbou
K. Kandu OiyGiri Harbor Development Project is well underway, with overall 59% project progress. We have completed construction of revetment. Scope of works include, harbor
R. Ungoofaaru Road Construction Project (phase 2) is well underway. Sidewalk paving works are ongoing with 98% completion. We have commenced ABC laying works. Scope of work
AA. Ukulhas Harbor Development Project is currently underway. Quay wall construction and harbor pavement installation work has been completed, and harbor dredging operation
The Ha. Muraidhoo Harbor Development Project is currently underway with 72% overall project progress. The second shipment of rock boulders has been delivered to the project
The Gn. Fuvahmulah Internal Roads Construction Project is currently ongoing with overall 86% project progress. Sub-base work has reached 92% completion, and sub grade work
Hdh. Kumundhoo Harbor Channel Project is currently underway with 62% overall project completion. The third shipment of rock boulders has been delivered to the project site,
Gdh. Gahdhoo Harbor Development Project is currently underway with 57% overall project completion. Quay wall block installation work has been completed, and quay wall concr
We have commenced physical work for the Sh. Milandhoo Harbor Development Project on 16th May 2023. New harbor basin dredging work is currently ongoing at the site. Scope of
Full shipment of rock boulders for the Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project has been delivered to the project site, and exist
Ha. Hoarafushi Road Development Project is currently underway with overall 82% project progress. Pavement installation work is currently ongoing at the site, and asphalt la
N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway with 50% project completion. Ramp construction work has begun, and jetty colum
We have commenced physical works of M. Maduvvari Harbor Development Project on 14th May 2023. Entrance channel dredging operations are currently ongoing. Scope of works inc
We have commenced breakwater profiling works for Ha. Muraidhoo Harbor Development Project. Bed preparation works are ongoing, with 55% completion. Completed scope of works
First shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the project site. Dredging and reclamation operations are ongo
We have commenced physical works of Sh. Narudhoo Harbor Development Project on 4th May 2023. New harbor basin dredging operations are currently ongoing. Scope of works incl
The second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the project site. Scope of works include Dred
Construction work for the Ha. Hoarafushi Juvenile Justice Unit (Halfway House) project has reached 50% completion. Roofing work has been completed, and ceiling and plsterin
M. Muli Harbor Development Project is well underway, with existing harbor basin dredging operations and installation of concrete blocks required for quay wall construction
B. Hithaadhoo Harbor Breakwater and Quay wall construction project is well underway. We have completed installation of precast concrete blocks required for quay wall constr
B. Hithaadhoo Harbor Breakwater and Quaywall Construction Project is well underway. We have completed existing harbor basin dredging operations. Full shipment of concrete b
First shipment of rock boulders required for Gdh. Rathafandhoo Shore Protection Project have been delivered to the site. Beach filling operations are ongoing, with 87% comp
Third shipment of rock boulders required for Sh. Milandhoo Shore Protection Project have been delivered to the site. Scope of works involve, construction of a 954m revetmen
New harbor basin dredging operations are ongoing for Adh. Dhigurah Harbor Development Project. Scope of works include, dredging operations of 64,416 cbm , channel dredging
Work on B. Kamadhoo Harbor Development Project is well underway, with overall 54% project progress. Third shipment of rock boulders have been delivered to the project site.
We have mobilized K. Maafushi Harbor Development Project site on 8th April 2023. Scope of works include, 63,711cbm of new harbor basin dredging operations, 28,836cbm of mai
We have mobilized K. Gulhi Land Reclamation and Shore Protection project site on 8th April 2023. Scope of works include, reclamation operations of 10.15 hectares, construct
Adh. Kunburudhoo Shore Protection Project is well underway. Dredging and reclamation operations are ongoing with 52% completion. Scope of works include, 24,000 cbm of dredg
First shipment of concrete blocks required for Sh. Maaungoodhoo Harbor Development Project have been delivered to the site. New harbor basin dredging operations are current
The second shipment of Rock Boulders required for the Sh. Milandhoo Shore Protection Project have been delivered to the project site. Groyne profiling work is currently ong
We have commenced physical works of Adh. Dhigurah Harbor Development Project on 8th March 2023. Scope of works include, dredging operations of 64,416 cbm , channel dredging
We have mobilized Sh. Narudhoo Harbor Development Project site on 1 March 2023. Scope of works include, 51,212cbm of harbor dredging operations, 4,120cbm of channel dredgin
We have mobilized Th. Vilufushi Shore Protection Project site on 24th Jan 2023. EIA works are currently ongoing. Scope of works include, dredging operations of 3,047cbm, sw
We have mobilized Ha. Thakandhoo Channel Breakwater Upgrade and Shore Protection Project site on 18th Jan 2023. Scope of works include, 4,455cbm of harbor dredging operatio
We have completed B. Dharavandhoo Coastal Protection Project. Scope of works include, construction of a 470m breakwater, 96m revetment and 10,800cbm beach filling operation
We have completed Sh. Noomaraa Harbor and Channel Dredging Project. Scope of works include 6347cbm harbor and channel dredging operations.
We have mobilized Ga. Villingili Harbor Development Project (Phase 3) site on 3rd Jan 2023. Scope of works include, dredging and excavation operations of 59,536.80 cbm harb
We have mobilized Sh. Noomaraa Harbor and Channel Dredging Project on 15th Dec 2022. Scope of works include, 6,347cbm maintenance dredging operations of existing harbor bas
We have commenced physical works of Gdh. Gahdhoo Harbor Development Project on 26th Nov 2022. Existing harbor channel closing work is currently ongoing. First shipment of r
We have completed construction of Hdh. Kumundhoo Ferry Hut. The Ferry Hut is being established under the purview of “Raajje Transport Link” Zone 1. Scope of wor
Gdh. Faresmaathoda Airport Development Project is currently underway, with overall 82% project progress. Fire building and terminal building construction works have reached
The third shipment of rock boulders required for the N. Velidhoo Boat Beaching Area Project has been delivered to the project site, and breakwater bed preparation works hav
We have mobilized K. Kandu Oiy Giri Harbor Development project site on 13th Nov 2022. Scope of works include, harbor dredging operations of 10,000cbm, channel dredging oper
Third shipment of rock boulders required for S. Hulhudhoo Harbor Development Project, have been delivered to the site. Construction of revetment is ongoing, with 94% comple
Breakwater construction for Lh. Kurendhoo Shore Protection Project has reached 86% completion, and beach filling works are currently ongoing at the site. Scope of works inc
We have commenced the R. Ungoofaaru channel relocation project works on 6th November 2022. Scope of works include, channel dredging operations of 41,980 cbm, construction o
The second shipment of Quay Wall blocks required for the B. Kamadhoo Harbor Reconstruction Project have been delivered to the project site. New harbor basin dredging works
The third shipment of rock boulders required for the B. Dharavandhoo Shore Protection Project have been delivered to the project site. Scope of works include 10,800 cbm of
We have completed B. Kendhoo Shore Protection Project. Scope of works include, dredging operation of 1200 cbm swimming area (40 x 20m), construction of a 803m breakwater, a
We have commenced physical works of Gdh. Thinadhoo Industrial Zone Land Reclamation and Shore Protection Project on 1st Nov 2022. Bund wall preparation works are currently
Second shipment of rock boulders required for runway shore protection works for Meemu Airport Development Project have been delivered to the site. Terminal building foundat
Quay wall concrete works and installation of harbor pavement are currently ongoing, with 97% and 49% completion respectively, for L. Gan Thundi Harbor Development Project.
Hdh. Nellaidhoo Shore Protection Project has reached 93% completion and currently, revetment construction works are ongoing at the site. Scope of works include, development
Ga. Dhaandhoo Harbor Development Project is currently underway. Quay Wall block installation and concrete works are currently ongoing at the project site. Scope of works in
We have completed construction of Ha. Thakandhoo Ferry Hut. This falls within the purview of Ferry Stops constructed at Zone 1 of “Raajje Transport Link” projec
Settlement tank installation work is currently ongoing under Phase 2 of the L. Fonadhoo Road Construction Project. Furthermore, we have completed 93% of stormwater pipe ins
Work on design and build of Ha. Muraidhoo Harbor Development Project is well underway, with overall 57% project progress, We have completed construction of quay wall. The s
Work on design and build of S. Hulhudhoo Harbor Development Project is well underway, with overall 93% project progress. Second shipment of rock boulders required for the p
First shipment of concrete blocks required for R. Maakurathu Harbor Development Project has been delivered to the project site on 21st September 2022. Currently, dredging w
Work on design and build of R. Kinolhas Harbor Development Project is well underway, with overall 60% project progress. We have completed channel dredging operations. Scope
N. Velidhoo Boat Beaching Area Project is well underway, with overall 56% project progress. Levelling of reclaimed area is currently ongoing, with 86% completion. Scope of
Second shipment of rock boulders required for the Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project has been delivered to the project site
Design and build of M. Muli Airport is currently underway. Runway reclamation and fire building plastering works are currently ongoing at the site, with 42% and 68% complet
Breakwater Construction work for the Lh. Hinnavaru Harbour Extension Project is currently under way with 86% work completion. Scope of works for the project include, reclam
The first shipment of rock boulders required for the M. Kolhufushi shore protection project was delivered to the project site on September 11th, 2022, and the dredging work
On September 11th, 2022, the second shipment of rock boulders required for the Lh. Kurendhoo shore protection project was delivered to the project site, and breakwater cons
We have commenced physical works of Ha. Hoarafushi Airport Jetty Construction Project on 7th Sep 2022. Scope of works include, channel dredging operations of 18,000cbm, con
MTCC has been awarded the shore protection project of the newly reclaimed land at M. Dhiggaru. The client is the Ministry of National Planning, Housing and Infrastructure o
Asphalt laying works for the GN. Fuvahmulah Internal Roads Construction Project was inaugurated today by Fuvahmulah City Mayor, Mr. Ismail Rafeeq Scope of works for the pro
H.E President Ibrahim Mohamed Solih has graced the ceremony held to mark the completion of M. Veyvah Harbor Development Project. Minister Mohamed Aslam, Minister Fayyaz Ism
Third shipment of precast concrete blocks required for quay wall construction for Sh. Lhaimagu Harbor Development Project, have been delivered to the site. Harbor basin dre
New harbor basin dredging operations for R. Maakurathu Harbor Development Project, is progressing, with 73% completion. Scope of works involve, 45,024cbm of harbor dredging
M. Dhiggaru Land Reclamation and Shore Protection Project is well underway, with overall 57% project progress. Reclamation operations are ongoing, with 68% completion. Scop
Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway, with overall 54% project progress. Installation of precast concrete blocks for quay wa
Work on design and build of Ha. Ihavandhoo Harbor is well underway, with overall 95% project progress. We have completed construction of breakwater. Scope of works for the
We have mobilized Gdh. Rathafandhoo Shore Protection Project on 7th August 2022. Scope of works include, construction of a 461m revetment, a 240m breakwater and beach filli
Work on Ha. Hoarafushi Airport Shore Protection Project is well underway, with overall 60% project progress. We have completed construction of breakwater and existing groyn
We have completed asphalt laying works for Hdh. Hanimaadhoo Road Development Project. In this regard, we completed asphalt laying works on 46,466 sqm. Scope of works involv
Full shipment of precast concrete blocks required for quay wall construction of Sh. Feydhoo Harbor, have been delivered to the project site. Preparations to commence quay w
Second shipment of rock boulders required for N. Velidhoo Boat Beaching Area project have been delivered to the project site. 85% of the reclamation works have been complet
Second shipment of precast concrete blocks required for quay wall construction of Ha. Dhihdhoo Harbor and Jetty Construction Project, have been delivered to the project sit
R. Dhuvaafaru Road Construction Project (Phase 2) is well underway, with overall 93% project progress. We have completed asphalt laying works. Scope of works involve, const
Work on design and build of Ha. Ihavandhoo Harbor Development Project is well underway, with overall 92% project progress. We have commenced installation of light post and
First shipment of rock boulders required for project works of K. Bandos Shore Protection Project (South – East) side have been delivered to the site. Scope of works i
We have completed quay wall concrete works for Lh. Hinnavaru Harbor Extension Project. Harbor pavement casting works are currently ongoing. Scope of works for the project i
Fuvahmulah City Internal Roads Construction Project is well underway with overall 72.65% project progress. Stormwater Drainage works are currently ongoing at site. Scope of
Work on Ha. Hoarafushi Airport Shore Protection Project is well underway, with overall 55% project progress. Breakwater profiling works and construction of groyne are curre
We have commenced construction of ferry hut on 1st June 2022 for Hdh. Kumundhoo Ferry Stop. Scope of works involve a kiosk, waiting area and toilets for customers. The ferr
Construction of groyne is currently ongoing for R. Rasmaadhoo Shore Protection Project. Project works involve, construction of a 336m groynes. The value of the project is M
Second shipment of precast concrete blocks required for quay wall construction of L. Gan Thundi Harbor Development Project have been delivered to the project site on 3rd Ju
Second shipment of rock boulders required for B. Kendhoo Coastal Protection Project have been delivered to the project site on 2nd June 2022. Swimming area dredging operati
The second shipment of rock boulders required for shore protection works of Ga. Dhaandhoo have been delivered to the project site on 01st June 2022. And Construction of san
Work on design and build of K. Himmafushi Harbor – Phase 2 is well underway, with overall 59% project progress. Breakwater construction has been completed and harbor
New harbor basin dredging operation are progressing with 75% completion, for Ha. Muraidhoo Harbor Development Project. The scope of the project includes, construction of a
Design and build of Adh. Mandhoo Harbor Development Project is well under way. New entrance channel dredging operations are ongoing with 89% completion. Scope of works for
Ga. Dhaandhoo Harbor Development Project is well underway. Dredging works are currently ongoing at the project site. Scope of works involve, 52,099cbm of harbor dredging op
Adh. Hangnaameedhoo Football Ground Levelling Works are ongoing. This is an initiative of our Corporate Social Responsibility. Scope of works involve, site clearing and com
First shipment of precast concrete blocks required for quay wall construction of Ha. Dhihdhoo Harbor Extension and Jetty Construction Project have been delivered to the pro
We have mobilized R. Maakurathu Harbor Development Project site on 20th May 2022. Scope of works involve, 45,024cbm of harbor dredging operations, construction of a 140m br
Maintenance dredging operations of harbor basin for Ha. Baarah Channel and Maintenance Dredging Project are ongoing, with 75% completion. Scope of works include, channel dr
We have commenced construction of bund wall in preparation for reclamation operations of R. Alifushi Land Reclamation and Airport Development Project. Scope of works involv
We have completed construction of ferry hut for Hdh. Neykurendhoo Ferry Stop. Scope of works involve a kiosk, waiting area and separate toilets for males and females. The f
We have completed harbor basin dredging operations for Hdh. Kumundhoo Harbor Channel Project. Channel dredging operations are currently ongoing, with 75% completion. Scope
Breakwater profiling works of AA. Maalhos Harbor Development Project is currently ongoing at 61% completion. We have already completed the dredging operations during March
The casting works & installation of electrical junction box & pipe laying works for Ha. Hoarafushi Road Construction Project are ongoing at 83% & 36% completion respectivel
We have mobilized B. Hithaadhoo Harbor Development project site on 11th May 2022. Scope of works include, dredging and excavation operations of 19,030cbm, construction of a
M. Dhiggaru Land Reclamation and Shore Protection project is well underway, with overall 50% project progress. 63% of revetment works have been completed and reclamation wo
Work on design and build of Ha. Ihavandhoo harbor development project is ongoing , with overall 88% project progress. Breakwater variation works are ongoing, with 95% compl
We have mobilized Sh. Milandhoo Shore Protection project site on 07th May 2022. Scope of works involve, construction of a 954m revetment and construction of a 115m groyne.
We have mobilized Gdh. Gahdhoo Harbor Development project site on 07th May 2022. Scope of works involve, dredging and excavation operations of 23,017 cbm, construction of a
The second shipment of rock boulders needed for Hdh. Nellaidhoo Shore Protection Project has been delivered to the project site. Revetment works are currently ongoing. Scop
Renovation works of Gdh.Thinadhoo Islamic Center has commenced on 05th May 2022.
The first shipment of rock boulders needed for B.Dharavandhoo Shore Protection Project has been delivered to the project site. Geo bag revetment works are currently ongoing
Under the Construction of Major Roads at R. Dhuvaafaru (2nd phase), asphalt works are progressing with 75% completion. Pavement works are ongoing with 91% completion. Stree
The first shipment of precast concrete blocks required for Lh. Felivaru Reclamation and Harbor Development Project has been delivered to the project site. 95% of the dredgi
Design and Build of Sh. Lhaimagu Harbour is well underway. The quay wall concrete block installation works of the project are ongoing, with 59% completion. Quay wall concre
We have commenced construction of revetment for N. Velidhoo Boat Beaching Area Project. Scope of works include, reclamation operations of 3.48 hectares and construction of
The construction of OPD Building of Kulhudhuffushi Regional Hospital is ongoing, with 53% completion. We have completed concrete, structural and roofing works of the OPD Bu
First shipment of rock boulders required for Lh. Hinnavaru Harbor Extension Project have been delivered to the project site on 24 April 2022. Concrete works of the quay wal
Materials required for water supply system for Th. Gaadhiffushi Water Supply and Sewerage Project have been delivered to the project site. Construction of parking shed is o
Maintenance dredging operations of harbor basin for Ha. Baarah Channel and Maintenance Dredging Project are ongoing, with 63% completion. Scope of works include, channel dr
We have mobilized Mahaa Jarraaf to the project site to commence reclamation operations at M. Dhiggaru. Scope of works involve, reclamation operations of 25 hectares, constr
We have successfully completed F. Dharanboodhoo Harbor Development Project. Scope of works include, dredging and excavation operations, construction of a breakwater, a quay
Work on design and build of Sh. Foakaidhoo Harbor Development Project is well underway, with overall 62% project progress. Fourth shipment of precast concrete blocks requir
Third shipment of rock boulders required for Aa. Maalhos Harbor Development Project have been delivered to the project site on 16th April 2022. Scope of works involve, dred
Work on design and build of S. Hulhudhoo Harbor Development Project is well underway, with overall 83% project progress. We have completed construction of quay wall. Harbor
We have completed installation of blocks for quay wall construction of Lh. Hinnvaru Harbor. The concrete works of quay wall are currently ongoing, with 57% completion. Scop
We have commenced physical works of Ga. Dhaandhoo Harbor Development Project on 29th March 2022. Scope of works involve, 52,099cbm of harbor dredging operations, 4953cbm of
First shipment of rock boulders required for V. Rakeedhoo Coastal Protection Project have been delivered to the project site on 27th March 2022. Project works involve, cons
Construction of Major Roads at R. Dhuvaafaru (2nd phase) is well underway, with overall 82% project progress. We have commenced asphalt works on 17,790 sqm of roads on 26th
Dredging operations of existing harbor channel for Sh. Lhaimagu Harbor is ongoing, with 61% completion. The installation of blocks required for quay wall construction and q
We have completed construction of walkway bridge for Th. Guraidhoo Harbor Development Project. Construction of breakwater is ongoing, with 88% completion. Project works con
Work on design and build of Adh. Hangnaameedhoo Harbor Development Project is well underway, with overall 72% project progress. Fifth shipment of precast concrete blocks re
Work on design and build of Sh. Bilehfahi Harbor Development Project is well underway, with overall 77% project progress. Third shipment of rock boulders required for proje
We have completed installation of blocks required for quay wall and new harbor basin dredging operations for K. Himmafushi Harbor Development Project (phase 2). Quay wall c
Work on design and build of Th. Guraidhoo Harbor Development Project is well underway, with overall 77% project progress. Second shipment of rock boulders have been deliver
First shipment of rock boulders required for Aa. Maalhos Harbor Development Project have been delivered to project site on 1 March 2022. We have completed channel dredging
Fifth shipment of rock boulders required for Ha. Ihavandhoo Harbor Development Project have been delivered to project site on 23 Feb 2022. Scope of works for the project in
We have completed harbor bridge column works for S. Hulhudhoo Harbor Development Project. Quay wall concrete works are currently ongoing. The S. Hulhudhoo Harbour project c
Dredging operations of swimming area for the Construction of Shore Protection Structures at M. Kolhufushi is ongoing, with 58% completion. Scope of works include, dredging
We have completed runway ABC works and subgrade works of Gdh. Faresmathoda Airport Development Project. Terminal Building Steel structure assembly work is currently ongoing
Construction of Major Roads at R. Dhuvaafaru (2nd phase) is well underway, with overall 65% project progress. We have completed subbase and subgrade works of carriageway an
Dredging and reclamation operations for Ha. Ihavandhoo land reclamation and shore protection project is ongoing, with 54% completion. We have commenced rock boulder revetme
Second shipment of rock boulders required for breakwater construction of K. Girifushi Harbor have been delivered to the project site on 13th Feb 2022. Breakwater bed prepar
Work on design and build of Hdh. Hanimaadhoo Harbor Development Project is well underway, with overall 55% project progress. Quay wall concrete works are ongoing. We have c
Dredging operations and footing casting works for jetty construction are currently ongoing, for N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project. Sco
We have completed Sh. Feevah Harbor Development Project on 29 Jan 2022. Scope of works include, dredging operations of 40,420 cbm, channel dredging operations of 14,743 cbm
Work on design and build of Sh. Bilehfahi Harbor Development Project is well underway, with overall 72% project progress. Second shipment of rock boulders required for brea
Work on design and build of R. Angolhitheem Harbor is well underway, with overall 80% project progress. Last shipment of rock boulders required for project work have been d
The second shipment of precast concrete blocks required for the quay wall construction of K. Himmafushi Harbor (phase 2) have been delivered to the project site on 4th Feb
The first shipment of precast concrete blocks required to commence quay wall construction of Sh. Lhaimagu Harbor have been delivered to the project site. The installation o
Work on design and build of R. Rasmaadhoo Harbor is well underway, with overall 80% project progress. We have completed installation of precast concrete blocks required for
L. Fonadhoo Road Construction Project (Phase 2) is well underway, with installation of stormwater management system currently ongoing. Scope of works include, construction
Work on design and build of Sh. Foakaidhoo Harbor is well underway, with overall 56% project progress. First shipment of precast concrete blocks required for quay wall cons
We have completed harbor basin dredging operations of Aa. Maalhos Harbor. MTCC continues investing on large machineries to avoid explosive blasting of hard strata removal.
Work on the design and build of Aa. Ukulhas Harbor Quay Wall and Jetty Construction is well underway, with overall, 92% project progress. We have commenced existing breakwa
Work on design and build of Shore Protection Structures at B. Thulhaadhoo is well underway, with overall 70% project progress. We have completed backfilling and bed prepara
Work on design and build of R. Rasmaadhoo Harbor is well underway, with overall 75% project progress. The first barge of precast concrete blocks required for quay wall cons
We have commenced ABC works of R. Dhuvaafaru Road Construction Project (Phase 2) on 8th January 2022. Scope of works involve, construction of 9 roads with a total length of
The 4th shipment of rock boulders required for Ha. Hoarafushi Airport Shore Protection have been delivered to the project site on 4 January 2022. Scope of works for the pro
The 3rd shipment of precast concrete blocks required for the quay wall construction of Hdh. Hanimaadhoo Harbor have been delivered to the project site on 4 January 2022. Th
We have commenced installation of precast concrete blocks for the quay wall construction of K. Himmafushi Harbor Development Project (phase 2). Scope of works include, dred
We have completed reclamation operations of K. Maafushi Picnic Island. The first shipment of rock boulders required for shore protection have been delivered to project site
We have commenced physical works of Adh. Mandhoo Harbor Development Project on 15th December 2021. Scope of works for the project include dredging and excavation operations
Installation of precast concrete blocks required for the construction of quay wall for Hdh. Hanimaadhoo Harbor is currently ongoing. The Hdh. Hanimaadhoo Harbour project co
Work on Sh. Feevah Football Ground Subbase Project is well underway, with overall 72% project progress. Installation of drainage gutter is currently ongoing, with 98% compl
We have commenced installation of stormwater pipe on 13th Dec 2021, for L. Fonadhoo Road Development Project (2nd phase). Scope of works includes, construction of a 27,179s
We have completed R. Fainu Shore Protection Project on 12th December 2021. Scope of works include, 8100cbm of sand backfilling and construction of a 250m geobag revetment.
We have completed B. Fehendhoo Harbor Development Project on 20th November 2021. Scope of works for the project include, harbor dredging and channel dredging operations, co
Work on design and build of R. Maduvvari South Harbor is well underway, with overall 90% project progress. The R. Maduvvari South Harbor development scheme consists of dred
Work on Gdh. Thinadhoo Dr. Abdul Samad Memorial Hospital Development Project is well underway, with overall 64% project progress. We have commenced installation of air cond
The construction of internal roads for Gn. Fuvahmulah is well underway, with overall 70% project progress. We have commenced installation of stormwater drainage system on 6
Work on design and build of F. Dharanboodhoo Harbor is well underway with overall 88% project progress. We have completed construction of harbor bridge. Construction of bre
We have commenced laying of sewerage pipeline for Th. Gaadhiffushi Water Supply & Sewerage Project on 29th Nov 2021. Construction of RO plant administrative building is cur
Dredging operations for sand required for beach filling for Th. Buruni Shore Protection Project has commenced today. Scope of works for the project include, beach filling o
New harbor basin dredging operations for Ha. Dhidhoo Harbor Extension and Jetty Construction Project is currently ongoing. Project works involve, dredging and excavation op
Harbor basin dredging operations of Sh. Feydhoo Harbor is currently ongoing, with 98% completion. The Sh. Feydhoo Harbour project consists of; dredging and excavation opera
Harbor basin dredging operations of R. Angolhitheem Harbor is currently ongoing, with 57% completion. The R. Angolhitheem Harbour project consists of; dredging and excavati
The first shipment of precast concrete blocks required for quay wall construction of Hdh. Hanimaadhoo Harbor have been delivered to project site on 17th Nov 2021. Existing
Work on design and build of N. Miladhoo Harbor is well underway, with overall 50% project progress. The first shipment of precast concrete blocks required for quay wall con
Work on design and build of Hdh. Nellaidhoo Harbor is well underway, with overall 91% project progress. Construction of breakwater is currently ongoing, with 84% completion
The second shipment of rock boulders required for breakwater construction of Sh. Feydhoo Harbor have been delivered to the project site. The Sh. Feydhoo Harbour project con
Work on R. Fainu Shore Protection Project is well underway, with overall 63% project progress. We have commenced construction of revetment for shore protection on 1st Novem
Work on design and build of Sh. Bilehfahi Harbor is well underway, with overall 53% project progress. We have completed construction of quay wall for Sh. Bilehfahi Harbor o
We have commenced rock profiling works on breakwater for V. Fulidhoo coastal protection project on 29th October 2021. Scope of the project include, dredging, backfilling an
The fourth shipment of rock boulders required for the construction of revetment at M. Dhiggaru have been delivered to the project site on 23rd October 2021. Scope of works
Work on Design and Build of N. Landhoo Harbour is well underway, with overall 72% project progress. The second shipment of rock boulders required for breakwater constructio
We have completed S. Hulhumeedhoo Bahaudheen Road Construction Project on 15th October 2021. Scope of works involve asphalt laying on this road of 2.2km in length and 8.8m
MTCC has signed with Ministry of National Planning, Housing and Infrastructure  towards implementing the design and build of Gdh.Madaveli-Hoadehdhoo Causeway Construction P
We have commenced physical works of N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project on 24th October 2021. Scope of works for the project include; dr
Work on the design and build of shore protection structures at M. Mulah is ongoing with overall 70% project progress. Construction of geobag revetment is currently ongoing.
We have completed K. Maafushi Land Reclamation and Shore Protection project on 27th September 2021. The K. Maafushi Land Reclamation and Shore Protection project consists o
We have completed K. Guraidhoo Picnic Island Reclamation and Shore Protection Project on 11th September 2021. The K. Guraidhoo Picnic Island Reclamation and Shore Protectio
We have completed K. Guraidhoo Land Reclamation and Shore Protection project on 27th September 2021. The K. Guraidhoo Land Reclamation and Shore Protection project consists
We have completed L. Isdhoo Harbor Development Project on 17th August 2021. Scope of works for the project include dredging and excavation operations of 31,820cbm; the cons
Work on Design and Build of N. Landhoo Harbour is well underway, with overall 70% project progress. We have completed installation of harbor pavement and commenced construc
The first shipment of rock boulders required for shore protection works of Ga. Dhaandhoo have been delivered to the project site on 9th October 2021. The Ga. Dhaandhoo Land
Road construction project of R. Ungoofaaru is well underway, with overall 87% project progress. We have completed all asphalt works within the project scope, that is on 14
Work on Design and Build of R. Rasmaadhoo Harbour is well underway, with overall 66% project progress. We have completed construction of breakwater. Dredging operation of n
Work on design and build of Ha. Ihavandhoo Harbor Development Project is ongoing, with overall 66% project progress. The final shipment of precast concrete blocks required
Work on the design and build of shore protection structures at M. Mulah is ongoing with overall 60% project progress. We have commenced construction of geobag revetment on
The first shipment of rock boulders required for the breakwater construction of Sh. Bilehfahi Harbor have been delivered to the project site on 28th September 2021. Scope o
We have completed M. Veyvah Harbour Development Project on 10th September 2021. The M. Veyvah Harbour project consists of; dredging and excavation operations of 77,831cbm;
We have mobilized Adh. Mandhoo Harbor Development project site on 21st September 2021. Scope of works for the project include dredging and excavation operations of 65,854cb
We have completed installation of precast concrete blocks and capping beam works required for the construction of quay wall of Lh. Hinnavaru Harbor. The installation of har
The fourth shipment of precast concrete blocks required for the construction of quay wall of S. Hulhudhoo Harbor have been delivered to the project site on 21st September 2
The second shipment of rock boulders required for Ha. Hoarafushi Airport Shore Protection Project have been delivered to the project site on 19th September 2021. Scope of w
We have commenced foundation footing works of the terminal building of Hdh. Hanimaadhoo ferry terminal on 19th September 2021. Hanimaadhoo ferry terminal is to be establish
The construction of Bahaudheen Road at S. Hulhumeedhoo is nearing completion, with overall 97% project progress. The installation of stormwater pump station is currently on
The rock boulders required for the construction of groyne for Hdh. Hanimaadhoo Harbour have been delivered to the project site on 14th September 2021. The Hdh. Hanimaadhoo
The second shipment of rock boulders required for breakwater construction for V. Fulidhoo coastal protection project have been delivered to the project site. Scope of the p
Cleaning, levelling, and sand back filling works of the path to waste disposal location of Sh. Bilehfahi are currently ongoing. This is an initiative undertaken under MTCC’
Work on the design and build of Aa. Ukulhas Harbor Quay Wall and Jetty Construction is well underway, with overall 84% project progress. We have completed installation of h
Work on Gdh. Thinadhoo Dr. Abdul Samad Memorial Hospital Development Project is well underway, with overall 57% project progress. The construction of OPD building and Labor
Work on design and build of S. Hulhudhoo Harbour is underway, with overall 68% project progress. The installation of precast concrete blocks and concrete works required for
The second shipment of rock boulders required for the breakwater construction of Adh. Hangnaameedhoo Harbor have been delivered to the project site on 4th September 2021. W
New harbor basin dredging and entrance channel dredging operations to a depth of 8.5MSL (Mean Sea Level) is currently ongoing for S. Hulhumeedhoo MIFCO Harbor Development P
We have completed installation of harbor pavement for F. Dharanboodhoo Harbor on 4th September 2021. The construction of sand-filled breakwater is currently ongoing at the
The first shipment of rock boulders required for the breakwater construction of Sh. Feydhoo Harbor have been delivered to the project site on 4th September 2021. New harbor
Work on the design and build of R. Angolhitheem Harbor is well underway, with overall 53% project progress. We have completed installation of harbor pavement. The R. Angolh
The final shipment of precast concrete blocks required for the construction of quay wall of Sh. Bilehfahi Harbor have been delivered to the project site on 30th August 2021
We have commenced construction of breakwater of Sh. Foakaidhoo Harbor on 15th August 2021. The Sh. Foaki