17 Aug New harbor basin dredging operations for R. Maakurathu Harbor Development Project, is progressing
New harbor basin dredging operations for R. Maakurathu Harbor Development Project, is progressing, with 73% completion.
Scope of works involve, 45,024cbm of harbor dredging operations, construction of a 140m breakwater, a 129m quay wall, a 85m revetment, a 28m groyne, and installation of 641sqm pavement. The value of the project is MVR 26.67 million.
Sorry, the comment form is closed at this time.