N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway. Jetty column installation work has been completed, and barbending & concrete works are currently ongoing. Construction works of concrete bridge is nearing completion.
Scope of works include, 13,216cbm existing harbor dredging operations, 17,450cbm entrance channel dredging operations, construction of a 183m breakwater; a 188m revetment, construction of a concrete bridge (4.5m x 244m), construction of south side concrete jetty (105m x 5m), construction of Ramp (10m x 10m), installation of navigational aids & mooring buoys. The value of the project is MVR 39.13 million.