06 Jun K. Kandu OiyGiri Harbor Development Project is well underway
K. Kandu OiyGiri Harbor Development Project is well underway, with overall 59% project progress. We have completed construction of revetment.
Scope of works include, harbor dredging operations of 10,000cbm, channel dredging operations of 10,000cbm, construction of a 125m quay wall, a 265m breakwater, a 63m revetment, installation of harbor pavement, harbor lights and navigational lights. The value of the project is MVR 36.13 million.