Hdh. Kulhudhuffushi Regional Hospital Renovation project is well underway

Hdh. Kulhudhuffushi Regional Hospital Renovation project is well underway, with overall 18% project progress. Casting of lift wall located on the first floor of the Ward Building is now complete. Construction of the staircase located on the first floor is currently ongoing, with 50% completion. Slab beam bottom and reinforcement works located on the second floor are also ongoing.
Scope of project works include construction of a laboratory building, ward building and renovation of the OPD area. The estimated value of the project is 30.3 million. The project was mobilized on 17th May 2020.