25 Jul Ha. Muraidhoo Harbor Development Project is well underway
Ha. Muraidhoo Harbor Development Project is well underway, with overall 90% project progress. We have completed breakwater profiling works.
Scope of works include, 28,175cbm new harbor basin dredging operations, 1,740cbm existing harbor basin dredging operations, 3,817cbm channel dredging operations, construction of a 264m quay wall; a 407m breakwater; a 275m revetment; a 50m groyne; installation of 1,933sqm harbor pavement, construction of a ramp, construction of 2 concrete bridges (15m x 2m), and installation of harbor lights. The value of the project is MVR 38.49 million.