25 Feb Ha. Baarah Channel and Maintenance Dredging Project is currently underway
Ha. Baarah Channel and Maintenance Dredging Project is currently underway with 84% project completion. Full shipment of Geobags has been delivered to the project site, and Channel dredging and maintenance dredging work for the project has been completed. Geobag revetment installation work is currently ongoing at the site with 58% progress.
Scope of works include, channel dredging operations of 79,100cbm, maintenance dredging operations of 8,600cbm, construction of 460m geobag revetment and installation of navigational lights. The value of the project is MVR 14.57 million.
Sorry, the comment form is closed at this time.