22 Jul Gdh. Rathafandhoo Shore Protection Project is well underway
Gdh. Rathafandhoo Shore Protection Project is well underway, with overall 60% project progress. We have completed construction of breakwater.
Scope of works include, construction of a 461m revetment; a 240m breakwater and 6,600cbm beach filling operations. The value of the project is MVR 26.27 million.