18 Feb Gdh. Rathafandhoo Shore Protection Project is well underway
Gdh. Rathafandhoo Shore Protection Project is well underway. Second shipment of rock boulders required for the project have been delivered to the project site. Construction of revetment is currently ongoing, with 48% completion.
Scope of works include, construction of a 461m revetment; a 240m breakwater and 6,600cbm beach filling operations. The value of the project is MVR 26.27 million.