First shipment of rock boulders required for Lh. Hinnavaru Harbor Extension Project have been delivered to the project site

First shipment of rock boulders required for Lh. Hinnavaru Harbor Extension Project have been delivered to the project site on 24 April 2022. Concrete works of the quay wall are ongoing, with 66% completion.
Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment. The value of the project is MVR 99.52 million.