02 Mar First shipment of rock boulders required for Aa. Maalhos Harbor Development Project have been delivered to project site
First shipment of rock boulders required for Aa. Maalhos Harbor Development Project have been delivered to project site on 1 March 2022. We have completed channel dredging operations.
Scope of works involve, dredging and excavation operations of 24,335cbm, construction of a 394m quay wall, a 407m breakwater, a 100m revetment, a 56m groyne, installation of 1970sqm harbor pavement, construction of a ramp and installation of harbor lights. The value of the project is MVR 56.9 million.
Sorry, the comment form is closed at this time.