03 Mar F. Nilandhoo Harbor Development Project is well underway
F. Nilandhoo Harbor Development Project is well underway. First shipment of concrete blocks required for quay wall construction have been delivered to the site. Harbor basin dredging operations are currently ongoing.
Scope of works include, 55,141cbm new harbor basin dredging operations, 6,933cbm channel dredging operations, 2367m quay wall, 261m breakwater, 75m revetment, construction of a ramp (11m x 11m), construction of a jetty (100 m x 2m), construction of a concrete bridge (18m x 2m), 1,151sqm pavement installation, harbor lights and mooring buoys installation. The value of the project is MVR 61.75 million.
Sorry, the comment form is closed at this time.