CEO Adam Azim has inspected the progress of Ha. Hoarafushi airport development project.

CEO Adam Azim has inspected the progress of Ha. Hoarafushi airport development project. The project is well underway with overall 84% project progress. Construction of runway, terminal building and fire building are currently ongoing, with 99%, 75% and 50% completion, respectively. Team MTCC is working around the clock to complete the project before 8th November 2020.
Airport construction work involves construction of a 37,425sqm runway, 8,635m of apron and taxiway, service roads at air and land side in front of terminal, construction of passenger terminal and fire building.