The first shipment of quay wall blocks required for the Hdh. Kurinbi Harbor Development Project have been delivered to the project site. Quay wall block installation work is currently ongoing at the site, and new harbor basin dredging operations have reached 51% completion. Scope of works...

The first shipment of quay wall blocks required for the Hdh. Neykurendhoo Harbor Development Project has been delivered to the project site, and quay wall block installation work commenced on 13th July 2024. Scope of works for this project include, new harbor dredging operations of 22,323cbm,...

The seventh shipment of rock boulders required for the Sh. Milandhoo Shore Protection project has been delivered to the site. Furthermore, the revetment profiling work and groyne installation work are in progress, with 55% and 65% completion, respectively. The overall project completion is currently at...

The third shipment of rock boulders required for the Ha. Dhidhoo Harbor Extension & Jetty project has been delivered to the site. Furthermore, the variation works of quay wall blocks installation and new harbor basin dredging are complete. Additionally, the progress of the existing harbor...

N. Kendhikulhudhoo Harbor Upgrade and Boat Beaching Area Project is well underway. New harbor basin dredging operations are currently ongoing, with 67% completion. Scope of works include, 28,393cbm new harbor basin dredging operations, 30,480cbm maintenance dredging operations, 12,968cbm channel dredging operations, 12,038cbm boat beaching area basin...

We have mobilized the project site for the ADh. Dhangethi Harbor Development Project on 18th April 2024. Scope of works for the project include, 35,500cbm land reclamation operations, 69,500cbm harbor dredging operations, 33,600cbm channel dredging operations, 7,800cbm swimming area dredging operations, construction of 675m revetment, 389m...

R. Ungoofaaru Land Reclamation and Shore Protection Project is well underway. Dredging and reclamation is ongoing, with 63% completion. Scope of works include, 10 hectares reclamation operations, 838.60m rock boulder revetment, 75m rock boulder groyne. The value of the project is MVR 71.08 million. #MTCCProjects #RayyithungeKunfuni [foogallery id="71562"]...

Work on F. Magoodhoo Land Reclamation and Shore Protection Project is well underway, with overall 50% project progress. We have completed island reclamation operations. Geo bag filling work is currently ongoing. Scope of works include, 17 hectares island reclamation operations, 30.8 hectares airport reclamation operations, 1,948m...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway. Jetty column installation work has been completed, and barbending & concrete works are currently ongoing. Construction works of concrete bridge is nearing completion. Scope of works include, 13,216cbm existing harbor dredging operations, 17,450cbm entrance...

We have successfully completed Ha. Hoarafushi Juvenile Justice Unit (Halfway House) Project. Scope of works include, ground works, concrete works, masonry and plastering, roofing and ceiling, doors and windows, finishing (tiling, painting & decorations), mechanical, electrical & plumbing, installation of a fire fighting system. The value...

Second shipment of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project, have been delivered to the project site. Scope of works include, 17,900cbm maintenance dredging operations, 72,938cbm new harbor basin dredging operations, 8,400cbm channel dredging operations, construction of a 583m breakwater;...

We have commenced installation of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project. Scope of works include, 17,900cbm maintenance dredging operations, 72,938cbm new harbor basin dredging operations, 8,400cbm channel dredging operations, construction of a 583m breakwater; a 316m quay wall; a...

Ha. Baarah Channel and Maintenance Dredging Project is well underway, with overall 70% project progress. We have completed channel dredging operations and harbor basin maintenance dredging operations. Scope of works include, 49,437.5cbm channel dredging operations, 8,600cbm maintenance dredging operations, construction of a 460m geobag revetment and...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is well underway، with overall 55% project progress. We have completed channel breakwater operations and construction of ramp. Scope of works for the project include; dredging and excavation operations of 29,038cbm; construction of a 195m breakwater; a...

Second shipment of concrete blocks required for quay wall construction for Sh. Narudhoo Harbor Development Project have been delivered to the site on 17th July 2023. New harbor basin dredging operations are ongoing, with 40% completion. Scope of works include, 51,212cbm of harbor dredging operations, 4,120cbm...

Second shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the site. Scope of works include, 24,000 cbm of dredging and reclamation operations, construction of a 430 m rockboulder revetment; a 185 m geotube revetment; and 7,171 cbm beach replenishment operations....

Quay wall block installation work for Sh. Maaungoodhoo Harbor Development Project has reached 98% progress. Quay wall concrete capping work is currently ongoing with 27% completion, and new harbor basin dredging work has reached 41% completion. Scope of works include, 59,013cbm of dredging operations, 3,245cbm of...

Hdh. Kumundhoo Harbor Channel Project is currently underway with 62% overall project completion. The third shipment of rock boulders has been delivered to the project site, and breakwater bed preparation work has reached 54% completion. Additionally, revetment construction has reached 64% completion. Scope of works for...

Full shipment of rock boulders for the Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project has been delivered to the project site, and existing revetment rectification work has reached 52% completion. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway with 50% project completion. Ramp construction work has begun, and jetty column installation has reached 52% completion. Dredging of existing harbor is currently ongoing at the site with 30% progress. Scope of works for...

We have commenced physical works of M. Maduvvari Harbor Development Project on 14th May 2023. Entrance channel dredging operations are currently ongoing. Scope of works include, harbor dredging operations of 38,800cbm, channel dredging operations of 54,093cbm, dredging/excavation of additional materials of 18,578.60cbm, reclamation operations of 111,471cbm,...

We have commenced breakwater profiling works for Ha. Muraidhoo Harbor Development Project. Bed preparation works are ongoing, with 55% completion. Completed scope of works include, new harbour basin dredging operations of 28,101cbm, construction of a 224m quay wall, installation of 1,933sqm harbor pavement, construction of a...

First shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the project site. Dredging and reclamation operations are ongoing with 65% completion. Scope of works include, 24,000 cbm of dredging and reclamation operations, construction of a 430 m rockboulder revetment;...

The second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the project site. Scope of works include Dredging & Excavation operations of 78,000cbm, construction of a 378m breakwater, construction of 58m Groynes; 478m revetment; 630m quay...

B. Hithaadhoo Harbor Breakwater and Quay wall construction project is well underway. We have completed installation of precast concrete blocks required for quay wall construction. Concrete works of quay wall are currently ongoing. Scope of works include, 14,929cbm of dredging and excavation operations, 4,101cbm of entrance...

B. Hithaadhoo Harbor Breakwater and Quaywall Construction Project is well underway. We have completed existing harbor basin dredging operations. Full shipment of concrete blocks required for quaywall construction have been delivered to the site. Scope of works include, 14,929cbm of dredging and excavation operations, 4,101cbm of...

First shipment of rock boulders required for Gdh. Rathafandhoo Shore Protection Project have been delivered to the site. Beach filling operations are ongoing, with 87% completion. Scope of works include, construction of a 461m revetment, a 240m breakwater and beach filling operations of 6600 cbm. The...

First shipment of concrete blocks required for Sh. Maaungoodhoo Harbor Development Project have been delivered to the site. New harbor basin dredging operations are currently ongoing with 32% completion. Scope of works include, 59,013cbm of dredging operations, 3,245cbm of channel dredging operations, construction of a 362m...

The third shipment of rock boulders required for the N. Velidhoo Boat Beaching Area Project has been delivered to the project site, and breakwater bed preparation works have been completed. Furthermore, breakwater profiling work is scheduled to begin next. Scope of works include, reclamation operations of...

Third shipment of rock boulders required for S. Hulhudhoo Harbor Development Project, have been delivered to the site. Construction of revetment is ongoing, with 94% completion. Scope of works include, 88,623cbm of new harbor basin dredging operations, construction of a 742m quay wall, a 50m breakwater,...

We have commenced physical works of Gdh. Thinadhoo Industrial Zone Land Reclamation and Shore Protection Project on 1st Nov 2022. Bund wall preparation works are currently ongoing. Scope of works include, reclamation operations of 10.6 hectares, construction of a 1521m revetment, a 555m quay wall, sheet...

Second shipment of rock boulders required for runway shore protection works for Meemu Airport Development Project have been delivered to the site. Terminal building foundation works are currently ongoing. Project works involve, reclamation operations of 14 hectares; coastal protection operations of 1,812m; construction of a 1200m...

Quay wall concrete works and installation of harbor pavement are currently ongoing, with 97% and 49% completion respectively, for L. Gan Thundi Harbor Development Project. Scope of works include, construction of a 360m breakwater, a 310m quay wall, a 2501 sqm harbor pavement, a bridge and...

First shipment of concrete blocks required for R. Maakurathu Harbor Development Project has been delivered to the project site on 21st September 2022. Currently, dredging works of new harbor basin is ongoing with 87% project completion. Scope of works involve, 45,024cbm of harbor dredging operations, construction...

Second shipment of rock boulders required for the Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project has been delivered to the project site on 13th September 2022. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi Komandoo with a 200m...

H.E President Ibrahim Mohamed Solih has graced the ceremony held to mark the completion of M. Veyvah Harbor Development Project. Minister Mohamed Aslam, Minister Fayyaz Ismail, Minister Ahmed Naseem, Minister Dr. Aishath Ali, Minister Ahmed Mahloof, MP Ikram Hassan, CEO Adam Azim and senior officials...

Third shipment of precast concrete blocks required for quay wall construction for Sh. Lhaimagu Harbor Development Project, have been delivered to the site. Harbor basin dredging operations are ongoing, with 58% completion. Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of...

Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway, with overall 54% project progress. Installation of precast concrete blocks for quay wall construction is ongoing, with 70% completion. Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction...