Column work on the ward building for H. Dh. Kulhudhuffushi Regional Hospital Renovation project has begun. We are planning foundation laying work during Aug first week. Construction work for the project which will create an accommodation space for patients began on 1st June 2020. [foogallery id="9263"]...

‘Tango 575’ tugboat and ‘Kurimagu’ barge have travelled from MTCC Precast Yard to R. Vandhoo to deliver concrete quay wall T-units needed for ongoing harbour development project at R. Vandhoo. The units were delivered to the island on 15th July 2020. [foogallery id="9230"]...

Rock boulders needed for shore protection component of K. Maafushi Land Reclamation and Shore Protection project have been delivered to the project site. 25 hectares of land reclamation needed for the project was completed on 14th June 2020. Overall project progress is 66%. As part of...

Reinforcement works and casting of trench blocks required for K. Thilafushi Harbour rehabilitation project is currently ongoing. The construction of carriageway work has commenced and is progressing well. The project involves harbour rehabilitation; waste processing; development of an administrative building, a workshop and civil works platform...

‫ށ. ފީވަކުގައި ފަށާފައިވާ ބަނދަރު ހެދުމުގެ މަޝްރޫއު ހިންގުމަށް ނަގަން ޖެހޭ ރުއްގަސް ނަގައި ހއ. ހޯރަފުށީގައި އަލަށް ތަރައްގީ ކުރާ އެއާޕޯޓު ސަރަހައްދުގައި އިންދުމުގުގެ މަސައްކަތް މިކުންފުނިން ވަނީ ކޮށްފައެވެ. މި ރުއްގަސް ނެގިފައިވަނީ މިނިސްޓްރީ އޮފް ނޭޝަނަލް ޕްލޭނިންގ، ހައުސިންގ އެންޑް އިންފްރާސްޓަރކްޗަތ، މިނިސްޓްރީ އޮފް ފިޝަރީޒް، މެރިން ރިސޯސަސް އެންޑް އެގްރިކަލްޗަރ އަދި އެންވަޔަރަމަންޓް ޕްރޮޓެކްޝަން އޭޖެންސީގެ އެއްބާރުލުމާއި އެހީތެރިކަމާ...

75% of storm water network installation works and 64% of ABC laying works needed for B. Eydhafushi road construction project are now complete. All asphalt materials needed to finish the project have also been delivered to the project site. The project includes developing all main roads...

Work is well underway for design and build of S. Meedhoo harbour upgrade; with 60% overall project progress.The scheme for this project involves existing harbour basin’s dredging operations of 35,496cbm; channel entrance dredging of 22,500cbm; the construction of a 115m rock boulder breakwater; a 496m...

Project works on the design and build of coastal protection structures at N. Fohdhoo is well underway, with 58% project progress. We are currently working on backfill area leveling works and geo bag filling which will be used for revetment construction. The project involves sand filtering...

Work is full swing for design and build of M. Veyvah harbor project with 3.5m concrete quay wall T-units needed for quay wall works transferred to the project site on 22nd June 2020. Currently, our team is preparing for quay wall installation. Dredging operations of 56,925cbm...

‘‪Koimala 5’ has undocked from MTCC boatyard following repairs and set sail to Thaa Atoll where she will continue ferry services. Repairs were made on the main engine, generator and battery set of the vessel. The vessel docked twice at MTCC boatyard during 2020 for...

‘Tango-575’ tug boat and ‘Hitha’ barge are now travelling from our Thilafushi worksite to deliver machinery and concrete quay wall T-units required for ongoing harbor development projects at M. Veyvah and L. Maavah. The units which are precasted by our specialized team will be delivered...

In-situ wall concreting works and quay wall block installation needed for the design and build of Sh. Komandoo harbour upgrade is well underway. The project received EIA approval on 12th November 2019, and was subsequently mobilized on 18th December 2019. The scheme for this project involves...

‪Our hopper suction dredger, Mahaa Jarraafu, berthed at MTCC Boat Yard at K.Thilafushi yesterday for its scheduled maintenance and servicing. The maintenance and servicing work will be carried out in-house by our specialized engineering team. We are working tirelessly to complete this work ahead of...

Work on S. Feydhoo Football Ground Sub-Base has resumed, after changing pitch orientation on request of Ministry of Youth, Sports and Community Empowerment. We intent to complete the project by 31st July 2020. The footballs grounds sub-base work involves excavation of mud material from the area;...

The asphalt paving works for S. Hulhumeedhoo, Bahaudheen road construction project is now complete. 50mm thick asphalt was laid along the 2.2 km road, and we are set to begin finishing works needed for project completion. S. Hulhumeedhoo Bahaudheen road construction work involves road construction; installation...

ގދ. ތިނަދޫ ދެކުނު އަވަށުގެ ފުޓްބޯޅަ ދަނޑުގެ ސަބްބޭސް ހެދުމުގެ މަސައްކަތް ވަނީ 8 ޖޫން 2020 ގައި ނިންމާފައެވެ. މިނިސްޓްރީ އޮފް ޔޫތް، ސްޕޯޓްސް އެންޑް ކޮމިއުނިޓީ އެމްޕަވަރމަންޓްގެ ފަރާތުން ހަވާލުކޮށްފައިވާ މިމަސައްކަތް ކުރިއަށް ގެންގޮސްފައިވަނީ އެ މިނިސްޓްރީއިން ދެއްވާފައިވާ ސްޕެސިފިކޭޝަންތަކާއި މިންގަނޑުތަކާ އެއްގޮތަށެވެ. އަދި ކޮވިޑް-19 އާއި ގުޅިގެން ދިމާވާ ލޮޖިސްޓިކަލް މައްސަލަތައް ހައްލުކޮށް، ޕްރިކޯޝަނަރީ ފިޔަވަޅުތަކާއިއެކު މިމަސައްކަތް ކުރިއަށް ގެންދެވުމުގައި...

The installation of storm water works is ongoing for B. Eydhafushi major roads construction project, with storm water tanks being placed at 20m intervals. The excavation for pipe placement is carried out by trained staff to meet engineering requirements. Overall, the B. Eydhafushi roads construction project...

We are conducting an As-Built survey at S. Maradhoo’s eastern side of the breakwater starting point near the channel. The survey will obtain dimensional and vertical data so constructed improvements can be undertaken. The survey is a part of reconstruction of S. Maradhoo harbor breakwater which...

On request of Ministry of Economic Development, we are pleased to facilitate bus transportation to support safe repatriation of 265 Bangladeshi workers residing in Maldives to Bangladesh, yesterday.‬ Evacuees were picked up Hulhumale’ Phase Two and transferred to Velana International Airport from where they departed to...

‪Our Kashavaru Showroom operations, which were temporarily suspended, has now safely resumed to fulfill customer demand. ‬Our sincere gratitude to all our staff at Showroom and Sawmill for going above and beyond to fulfill customer requests from across various industries. We continue to monitor the situation...

The installation of pre-casted quay wall blocks for N. Henbadhoo harbour upgrade is well underway, with 60% overall project progress. Pre-casted blocks from our Thilafushi site were transferred to N. Henbadhoo to construct a 203m quay wall. Overall, the N. Henbadhoo harbour upgrade consists of dredging...

‪The construction of major roads for R. Dhuvaafaru road construction project is well underway, with 54% project progress. The road drainage system designed for R. Dhuvaafaru is an infiltration system which ensures rainwater is infiltrated into the freshwater lens of the island‬ instead of pumping...

Upon request of island councils, we have scheduled special ferries to solve logistical difficulties faced in transporting goods to and from various islands. The delivery of goods to 9 atolls, using 13 delivery routes, are currently underway. [foogallery id="8416"]...

‪On request of Indian High Commission in Maldives, we are pleased to facilitate bus transportation to support safe repatriation of Indians residing in Maldives to India under operation #SamundraSetu yesterday.‬ ‪Evacuees were picked up from both Fenna Gimatha and Greater Male Bus Terminal and transferred to...

We have commenced disinfection and sanitization procedures of ferries and both ferry terminals used in current Vilimale’ ferry operations as one of our frontline workers has tested positive for Covid19, today. The remaining seven frontline workers who resided at the terminal since last week are now...

[foogallery id="8194"] We have handed over the accommodation and storage facility we developed on the 100k sqft land plot I-1 at K. Gulhifalhu to National Disaster Management Authority - Maldives to increase the isolation capacity amid the #Covid19 outbreak in the country. Additional work to convert...

Laying of Aggregate Base Course (ABC layer) and pavement works for R. Dhuvaafaru road construction project are underway, with 38% project progress.The ABC layer which is placed on top of the Sub-Grade provides a stable foundation and increases the durability of roads. The project, which was...

‪We have completed 84% reclamation of the first island and 75% reclamation for the second island of Centara Three Islands Reclamation project. The construction of a groyne and revetment to mitigate the effects of erosion are ongoing for the first island. Three islands from a lagoon in...

The setting-out survey of breakwater, revetment and quay wall for V. Felidhoo Harbour extension project was completed on March 28,2020. The work focuses on detailed surveys including bathymetry of basin and channel; bathymetry of potential harbor expansion area; elevation profile from harbour area to the vegetation...

3300 tonnes of rock boulders needed for R. Madduvari South Harbour project have been delivered. The rock boulders will be used for breakwater construction. Additional rocks are needed for breakwater profiling to commence. The project, worth over MVR 68.6 million, includes dredging harbour basin and entrance channel,...

The harbor construction work for ‘Design and Build of harbor in N. Miladhoo’ project is moving forward swiftly. Machinery including excavators, diesel tank and welding genset were mobilized to N. Miladhoo on Leema 2, last night. Dredging is scheduled to start on March 28, 2020. (Saturday) A...

The project was inaugurated by Indian High Commisioner to the Maldives H.E Sanjay Sudhir. Dignitaries who graced the occasion included the Minister of National Planning and Infrastructure Mr. Mohamed Aslam, Minister of State for National Planning and Infrastructure Mr. Akram Kamaludheen and Chief Executive Officer of...

K. Maafushi land reclamation project was officially inaugurated in a ceremony held yesterday, 25th December 2019 at K. Maafushi. The event was attended by special guest, the president’s advisor Mohamed Shihab, Minister of National Planning and Infrastructure Mohamed Aslam, CEO of MTCC Hassan Shah, Maafushi island councilor Usman Rasheed, other...

The Maldives National Boating Awards 2019, organized by the National Boating Association of Maldives (NBAM) was held on the 23rd of December at Dharubaaruge. The boating awards began in the year 2014 to recognize the strength of boating industry and services rendered by the service providers. Maldives...

Yesterday, on the 18th of December 2019, we kicked off our 39th anniversary celebrations with a special cake cutting ceremony held at Fenna Gimatha for all MTCC staff. During the ceremony COO, Shahid Hussain Moosa and Chairman, Mohamed Faheem shared some insights with our team. Anniversary celebrations also...

MTCC has commenced it’s annual “Kashavaru Promo” on the 10th of December 2019. The launching event at Kashavaru Showroom was attended by Shifau Ali, general manager of MTCC and other officials from the company. Customers who visit during this campaign will get special discounts from Yanmar...

In celebration of World Customer Service Week, MTCC has launched a company-wide customer service campaign “Hinithunvumaaeku”. The purpose of this campaign is to create awareness among staff about the importance of customer relations and to improve the customer experience of everyone using MTCC’s services, in...

The 2018 Annual General Meeting of Maldives Transport and Contracting Company Plc was held on 08th July 2019 at Hotel Jen.  A total of 1695 shareholders and 5,756,392 shares were represented at the Annual General Meeting 2018 Shareholder voting was carried out entirely through e-voting. The following was approved by the shareholders...

A road safety awareness training for bus drivers has been carried out by MTCC on May 13th 2019. This training aims to increase awareness of regulations surrounding vehicles, and to ensure safety for both passengers and pedestrians when traveling. This training was carried out in...

A road traffic awareness session was carried out for MTCC's transport department by Maldives Police Service on 20th Jan 2019. The session which mainly focused on road safety rules and regulations was attended by our bus operators and conductors. MTCC provides bus service within Hulhumale', along its...

HEP Yameen Abdul Gayyoom has officially inaugurated GA. Madaveli Harbour Project on 8th of August 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior...

An awareness program was carried out in AA. Ukulhas for Suzuki customers from islands of AA. Atoll including Ukulhas, Mathiveri, Bodufulhadhoo and Himandhoo from 12th to 13th Sep 2018. The participants included captains, crew and owners of vessels operating on Suzuki Outboard Engines within the atoll. The...

HEP Yameen Abdul Gayyoom has officially inaugurated L. Hithaadhoo Harbour Project on 8th of September 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior...

HEP Yameen Abdul Gayyoom has officially inaugurated L. Maabaidhoo Harbour Project on 8th of September 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior...

HEP Yameen Abdul Gayyoom has officially inaugurated Adh. Dhangethi Harbour Project on Monday, 3rd of September 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other...

HEP Yameen Abdul Gayyoom has officially inaugurated Lh. Naifaru Project on Monday,31st of August 2018. The event was attended by Minister of Environment and Energy Mr. Ibrahim Thoriq, Minister of Housing and Infrastructure Dr. Mohamed Muizzu, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior government officials...

MTCC carried out Suzuki Clean-up the world campaign on Friday, 31st of August 2018 in K. Maafushi. The event was carried out in collaboration with Save the Beach, K. Maafushi School, K. Maafushi council, Maldives Correctional Service, STELCO, local guesthouses and dive centers based in K. Maafushi. With...

HEP Yameen Abdul Gayyoom attends special function held to mark the completion of N. Velidhoo Coastal Protection project. The event was also attended by Minister of environment and energy Mr. Thoriq Ibrahim, Minister of  housing and infrastructure Dr. Mohamed Muizzu, members of parliament, MTCC CEO Ibrahim Ziyath...

HEP Yameen Abdul Gayyoom has officially inaugurated N. Maafaru harbour project yesterday. The event was also attended by Minister of  housing and infrastructure dr. Mohamed Muizzu, Minister of environment and energy Mr. Thoriq Ibrahim, members of parliament, MTCC CEO Ibrahim Ziyath and other senior officials from government and...

HEP Yameen Abdul Gayyoom attends special function held in Hdh. Nolhivaranfaru to mark the completion of harbour developmental project of Nolhivaranfaru island carried out by MTCC. The event was also attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy, Mr. Ibrahim Thoriq, CEO of...

HEP Yameen Abdul Gayyoom attended special function held to mark the completion of Th. Madifushi Land Reclamation and Coastal Protection project. The event was also attended by Minister of environment and energy Mr. Thoriq Ibrahim, Minister of  housing and infrastructure Dr. Mohamed Muizzu, members of parliament, MTCC CEO...

HEP Yameen Abdul Gayyoom has officially inaugurated Gdh. Madaveli Harbour Project on 8th of August 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior...

HEP Yameen Abdul Gayyoom has officially inaugurated Gdh. Gahdhoo harbour project on 7th of August 2018. The event was attended by Minister of Housing and Infrastructure Dr. Mohamed Muizzu, Minister of Environment and Energy Mr. Ibrahim Thoriq, CEO of MTCC Mr. Ibrahim Ziyath, Members of parliament, other senior...