Breakwater construction for Lh. Kurendhoo Shore Protection Project has reached 86% completion

Breakwater construction for Lh. Kurendhoo Shore Protection Project has reached 86% completion, and beach filling works are currently ongoing at the site.

Scope of works include, 91,000cbm beach filling, construction of a 361m breakwater and a 822m revetment. The value of the project is MVR 44.8 million.