Quay wall block installation work for Sh. Maaungoodhoo Harbor Development Project has reached 98% progress. Quay wall concrete capping work is currently ongoing with 27% completion, and new harbor basin dredging work has reached 41% completion. Scope of works include, 59,013cbm of dredging operations, 3,245cbm of...

Hdh. Kumundhoo Harbor Channel Project is currently underway with 62% overall project completion. The third shipment of rock boulders has been delivered to the project site, and breakwater bed preparation work has reached 54% completion. Additionally, revetment construction has reached 64% completion. Scope of works for...

Full shipment of rock boulders for the Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project has been delivered to the project site, and existing revetment rectification work has reached 52% completion. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway with 50% project completion. Ramp construction work has begun, and jetty column installation has reached 52% completion. Dredging of existing harbor is currently ongoing at the site with 30% progress. Scope of works for...

The second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the project site. Scope of works include Dredging & Excavation operations of 78,000cbm, construction of a 378m breakwater, construction of 58m Groynes; 478m revetment; 630m quay...

The third shipment of rock boulders required for the N. Velidhoo Boat Beaching Area Project has been delivered to the project site, and breakwater bed preparation works have been completed. Furthermore, breakwater profiling work is scheduled to begin next. Scope of works include, reclamation operations of...

First shipment of concrete blocks required for R. Maakurathu Harbor Development Project has been delivered to the project site on 21st September 2022. Currently, dredging works of new harbor basin is ongoing with 87% project completion. Scope of works involve, 45,024cbm of harbor dredging operations, construction...

Second shipment of rock boulders required for the Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project has been delivered to the project site on 13th September 2022. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi Komandoo with a 200m...