The first shipment of quay wall blocks required for the Hdh. Kurinbi Harbor Development Project have been delivered to the project site. Quay wall block installation work is currently ongoing at the site, and new harbor basin dredging operations have reached 51% completion. Scope of works...

The first shipment of quay wall blocks required for the Hdh. Neykurendhoo Harbor Development Project has been delivered to the project site, and quay wall block installation work commenced on 13th July 2024. Scope of works for this project include, new harbor dredging operations of 22,323cbm,...

The seventh shipment of rock boulders required for the Sh. Milandhoo Shore Protection project has been delivered to the site. Furthermore, the revetment profiling work and groyne installation work are in progress, with 55% and 65% completion, respectively. The overall project completion is currently at...

N. Kendhikulhudhoo Harbor Upgrade and Boat Beaching Area Project is well underway. New harbor basin dredging operations are currently ongoing, with 67% completion. Scope of works include, 28,393cbm new harbor basin dredging operations, 30,480cbm maintenance dredging operations, 12,968cbm channel dredging operations, 12,038cbm boat beaching area basin...

We have mobilized the project site for the ADh. Dhangethi Harbor Development Project on 18th April 2024. Scope of works for the project include, 35,500cbm land reclamation operations, 69,500cbm harbor dredging operations, 33,600cbm channel dredging operations, 7,800cbm swimming area dredging operations, construction of 675m revetment, 389m...

R. Ungoofaaru Land Reclamation and Shore Protection Project is well underway. Dredging and reclamation is ongoing, with 63% completion. Scope of works include, 10 hectares reclamation operations, 838.60m rock boulder revetment, 75m rock boulder groyne. The value of the project is MVR 71.08 million. #MTCCProjects #RayyithungeKunfuni [foogallery id="71562"]...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway. Jetty column installation work has been completed, and barbending & concrete works are currently ongoing. Construction works of concrete bridge is nearing completion. Scope of works include, 13,216cbm existing harbor dredging operations, 17,450cbm entrance...

We have successfully completed Ha. Hoarafushi Juvenile Justice Unit (Halfway House) Project. Scope of works include, ground works, concrete works, masonry and plastering, roofing and ceiling, doors and windows, finishing (tiling, painting & decorations), mechanical, electrical & plumbing, installation of a fire fighting system. The value...

Second shipment of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project, have been delivered to the project site. Scope of works include, 17,900cbm maintenance dredging operations, 72,938cbm new harbor basin dredging operations, 8,400cbm channel dredging operations, construction of a 583m breakwater;...

We have commenced installation of concrete blocks required for quay wall construction for Sh. Milandhoo Harbor Development Project. Scope of works include, 17,900cbm maintenance dredging operations, 72,938cbm new harbor basin dredging operations, 8,400cbm channel dredging operations, construction of a 583m breakwater; a 316m quay wall; a...

Ha. Baarah Channel and Maintenance Dredging Project is well underway, with overall 70% project progress. We have completed channel dredging operations and harbor basin maintenance dredging operations. Scope of works include, 49,437.5cbm channel dredging operations, 8,600cbm maintenance dredging operations, construction of a 460m geobag revetment and...

Second shipment of concrete blocks required for quay wall construction for Sh. Narudhoo Harbor Development Project have been delivered to the site on 17th July 2023. New harbor basin dredging operations are ongoing, with 40% completion. Scope of works include, 51,212cbm of harbor dredging operations, 4,120cbm...

Meemu Airport Development Project is well underway, with overall 60% project progress. We have completed airport shore protection revetment works. In addition, subgrade works for fire road and fire pad have been completed. Project works involve, reclamation operations of 14 hectares; coastal protection operations of 1,812m;...

Second shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the site. Scope of works include, 24,000 cbm of dredging and reclamation operations, construction of a 430 m rockboulder revetment; a 185 m geotube revetment; and 7,171 cbm beach replenishment operations....

Quay wall block installation work for Sh. Maaungoodhoo Harbor Development Project has reached 98% progress. Quay wall concrete capping work is currently ongoing with 27% completion, and new harbor basin dredging work has reached 41% completion. Scope of works include, 59,013cbm of dredging operations, 3,245cbm of...

Full shipment of rock boulders for the Sh. Komandoo Shore Protection Rectification and Mathi-Komandoo Connectivity Project has been delivered to the project site, and existing revetment rectification work has reached 52% completion. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi...

N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project is currently underway with 50% project completion. Ramp construction work has begun, and jetty column installation has reached 52% completion. Dredging of existing harbor is currently ongoing at the site with 30% progress. Scope of works for...

We have commenced physical works of M. Maduvvari Harbor Development Project on 14th May 2023. Entrance channel dredging operations are currently ongoing. Scope of works include, harbor dredging operations of 38,800cbm, channel dredging operations of 54,093cbm, dredging/excavation of additional materials of 18,578.60cbm, reclamation operations of 111,471cbm,...

First shipment of rock boulders required for Adh. Kunburudhoo Shore Protection Project have been delivered to the project site. Dredging and reclamation operations are ongoing with 65% completion. Scope of works include, 24,000 cbm of dredging and reclamation operations, construction of a 430 m rockboulder revetment;...

The second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the project site. Scope of works include Dredging & Excavation operations of 78,000cbm, construction of a 378m breakwater, construction of 58m Groynes; 478m revetment; 630m quay...

First shipment of rock boulders required for Gdh. Rathafandhoo Shore Protection Project have been delivered to the site. Beach filling operations are ongoing, with 87% completion. Scope of works include, construction of a 461m revetment, a 240m breakwater and beach filling operations of 6600 cbm. The...

The third shipment of rock boulders required for the N. Velidhoo Boat Beaching Area Project has been delivered to the project site, and breakwater bed preparation works have been completed. Furthermore, breakwater profiling work is scheduled to begin next. Scope of works include, reclamation operations of...

Third shipment of rock boulders required for S. Hulhudhoo Harbor Development Project, have been delivered to the site. Construction of revetment is ongoing, with 94% completion. Scope of works include, 88,623cbm of new harbor basin dredging operations, construction of a 742m quay wall, a 50m breakwater,...

Second shipment of rock boulders required for runway shore protection works for Meemu Airport Development Project have been delivered to the site. Terminal building foundation works are currently ongoing. Project works involve, reclamation operations of 14 hectares; coastal protection operations of 1,812m; construction of a 1200m...

Quay wall concrete works and installation of harbor pavement are currently ongoing, with 97% and 49% completion respectively, for L. Gan Thundi Harbor Development Project. Scope of works include, construction of a 360m breakwater, a 310m quay wall, a 2501 sqm harbor pavement, a bridge and...

Second shipment of rock boulders required for the Sh. Komandoo shore protection rectification and Mathi-Komandoo connectivity project has been delivered to the project site on 13th September 2022. Scope of works involve, reclamation operations of 16.7 hectares and connecting Komandoo and Mathi Komandoo with a 200m...

H.E President Ibrahim Mohamed Solih has graced the ceremony held to mark the completion of M. Veyvah Harbor Development Project. Minister Mohamed Aslam, Minister Fayyaz Ismail, Minister Ahmed Naseem, Minister Dr. Aishath Ali, Minister Ahmed Mahloof, MP Ikram Hassan, CEO Adam Azim and senior officials...

Third shipment of precast concrete blocks required for quay wall construction for Sh. Lhaimagu Harbor Development Project, have been delivered to the site. Harbor basin dredging operations are ongoing, with 58% completion. Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of...

Full shipment of precast concrete blocks required for quay wall construction of Sh. Feydhoo Harbor, have been delivered to the project site. Preparations to commence quay wall construction works are in motion. The scope of the project includes, dredging operations of 27,500cbm, construction of a 276m...

Second shipment of rock boulders required for N. Velidhoo Boat Beaching Area project have been delivered to the project site. 85% of the reclamation works have been completed. Revetment works are currently ongoing with 58% completion. Scope of works include, reclamation operations of 3.48 hectares and...

Second shipment of precast concrete blocks required for quay wall construction of Ha. Dhihdhoo Harbor and Jetty Construction Project, have been delivered to the project site on 23rd June 2022. Installation of blocks are currently ongoing. Project works involve, dredging and excavation operations of 78,000cbm; construction...

Work on design and build of Ha. Ihavandhoo Harbor Development Project is well underway, with overall 92% project progress. We have commenced installation of light post and construction of revetment. Scope of works for the project include dredging and excavation operations of 30,509cbm; the construction of...

First shipment of rock boulders required for project works of K. Bandos Shore Protection Project (South - East) side have been delivered to the site. Scope of works involve construction of a 557m breakwater. The client of this project is Orchid Holdings Pvt Ltd.[foogallery id="44325"] ...

Fuvahmulah City Internal Roads Construction Project is well underway with overall 72.65% project progress. Stormwater Drainage works are currently ongoing at site. Scope of works for the project include sub base preparation of 122,659sqm; an asphalt wearing course of 95, 239 sqm; footpath preparation of 27,450sqm;...

Second shipment of precast concrete blocks required for quay wall construction of L. Gan Thundi Harbor Development Project have been delivered to the project site on 3rd June 2022. Scope of works include, construction of a 360m breakwater, a 310m quay wall, a 2501 sqm harbor...

Second shipment of rock boulders required for B. Kendhoo Coastal Protection Project have been delivered to the project site on 2nd June 2022. Swimming area dredging operations are currently ongoing. Scope of works for the project include dredging operations of swimming track, construction of a 803m...

The second shipment of rock boulders required for shore protection works of Ga. Dhaandhoo have been delivered to the project site on 01st June 2022. And Construction of sand bund wall work has been completed. The Ga. Dhaandhoo Land Reclamation and Shore Protection project consists of;...

Design and build of Adh. Mandhoo Harbor Development Project is well under way. New entrance channel dredging operations are ongoing with 89% completion. Scope of works for the project include dredging and excavation operations of 65,854cbm; the construction of a 236m quay wall; a 319m breakwater;...

Ga. Dhaandhoo Harbor Development Project is well underway. Dredging works are currently ongoing at the project site. Scope of works involve, 52,099cbm of harbor dredging operations, 4953cbm of channel dredging operations, construction of a 30m groyne, a 333m breakwater, a 170m revetment, a 529m quay wall,...

First shipment of precast concrete blocks required for quay wall construction of Ha. Dhihdhoo Harbor Extension and Jetty Construction Project have been delivered to the project site on 24th May 2022. Harbor basin dredging operations are currently ongoing. Project works involve, dredging and excavation operations of...

Maintenance dredging operations of harbor basin for Ha. Baarah Channel and Maintenance Dredging Project are ongoing, with 75% completion. Scope of works include, channel dredging operations of 28,101cbm and installation of navigational lights. The value of the project is MVR 12.17 million. [foogallery id="41722"] ...

We have commenced construction of bund wall in preparation for reclamation operations of R. Alifushi Land Reclamation and Airport Development Project. Scope of works involve, reclamation operations of 50.5 hectares, construction of a 2871m revetment, a 480m groyne, construction of runway, apron, taxiway, and service roads,...

We have completed harbor basin dredging operations for Hdh. Kumundhoo Harbor Channel Project. Channel dredging operations are currently ongoing, with 75% completion. Scope of works incude, 9346.56 cbm of new harbor basin dredging operations, 4954.91 cbm of entrance channel dredging operations, construction of a 142m breakwater,...

Breakwater profiling works of AA. Maalhos Harbor Development Project is currently ongoing at 61% completion. We have already completed the dredging operations during March 2022. Overall project progress is now at 45% completion. Scope of works involve, dredging and excavation operations of 24,335cbm, construction of a...

The casting works & installation of electrical junction box & pipe laying works for Ha. Hoarafushi Road Construction Project are ongoing at 83% & 36% completion respectively. Additionally, curbstone installation works are now ongoing. The scope of the project includes, construction of 11 roads measuring 5.3km...

M. Dhiggaru Land Reclamation and Shore Protection project is well underway, with overall 50% project progress. 63% of revetment works have been completed and reclamation works are currently ongoing. Scope of works involve, reclamation operations of 25 hectares, construction of a 384m rock boulder revetment, a...

The first shipment of rock boulders needed for B.Dharavandhoo Shore Protection Project has been delivered to the project site. Geo bag revetment works are currently ongoing. Scope of works include 10,800 cbm of beach filling, construction of a 490m breakwater and a 96m revetment. The value...

Under the Construction of Major Roads at R. Dhuvaafaru (2nd phase), asphalt works are progressing with 75% completion. Pavement works are ongoing with 91% completion. Street lights required for the project has been delivered to the project site. Scope of works involve, construction of 9 roads...

The first shipment of precast concrete blocks required for Lh. Felivaru Reclamation and Harbor Development Project has been delivered to the project site. 95% of the dredging and reclamation works have been completed. Scope of works for the project include, reclamation operations of 6 hectare; dredging...

Design and Build of Sh. Lhaimagu Harbour is well underway. The quay wall concrete block installation works of the project are ongoing, with 59% completion. Quay wall concrete works are also currently ongoing. Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction...

Materials required for water supply system for Th. Gaadhiffushi Water Supply and Sewerage Project have been delivered to the project site. Construction of parking shed is ongoing, with 95% completion. Scope of works include, a 4070m sewerage network, a 210m pumping main and outfall and installation...

We have completed installation of blocks required for quay wall and new harbor basin dredging operations for K. Himmafushi Harbor Development Project (phase 2). Quay wall concrete works are currently ongoing. Scope of works include, dredging and excavation operations of 14,300cbm for new harbor basin, construction...

Dredging operations of swimming area for the Construction of Shore Protection Structures at M. Kolhufushi is ongoing, with 58% completion. Scope of works include, dredging operations of 9683cbm, construction of a 202m breakwater, a 519m revetment. The value of the project is MVR 22.9 million. [foogallery id="35352"] ...

Dredging and reclamation operations for Ha. Ihavandhoo land reclamation and shore protection project is ongoing, with 54% completion. We have commenced rock boulder revetment works and is progressing well. The Ha. Ihavandhoo Land Reclamation and Shore Protection project consists of; 25 hectares of land reclamation; construction...

Second shipment of rock boulders required for breakwater construction of K. Girifushi Harbor have been delivered to the project site on 13th Feb 2022. Breakwater bed preparation works are currently ongoing. Scope of works include construction of a 268m breakwater and a 46m channel breakwater. The...

Dredging operations and footing casting works for jetty construction are currently ongoing, for N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project. Scope of works for the project include; dredging and excavation operations of 29,038cbm; construction of a 195m breakwater; a 188m revetment; a concrete bridge;...

The second shipment of precast concrete blocks required for the quay wall construction of K. Himmafushi Harbor (phase 2) have been delivered to the project site on 4th Feb 2022. New harbor basin dredging operations are ongoing with 99% completion. Scope of works include, dredging and...